Dept. of Trans. PROGRESS Serial No. Contract No. 06-297-15-29 07-201704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 83% 07-LA-60-29.4/ .0 Federal Project: NONE Progress payment No. 08 Payment period ending: 10-20-06 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 02214 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,042,897.08 381,632.00 2.a. Extra Work 4,419.02 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,047,316.10 381,632.00 5. Mobilization 6. Total Work Completed 2,047,316.10 7. Deductions -113,867.70 0.00 8. a.Contract Retentions -204,731.61 -38,163.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,728,716.79 343,468.80 10. Reduction Amt to Escrow 11. Payment to Escrow 204,730.00 12. Net Pymt. this Estimate 343,468.80