Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-14-02 07-202114 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 85% Location: Federal Project: 07-LA-710-17.2/26.4 ACNH-7101(809) Progress payment No. 065 Payment period ending: 06-20-17 SHIMMICK/MYERS AND SONS JV 16481 SCIENTIFIC WAY IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,270,494.13 -88,601.40 2. a. Extra Work 8,294,470.66 328,393.43 b. Adustment Comp. 2,612,136.74 -93,015.10 3. Materials on Hand 4. Earned Subject to Retention 93,177,101.53 146,776.93 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 99,177,101.53 7. Deductions -28,100.00 22,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 99,149,001.53 168,776.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 168,776.93