Dept. of Trans. PROGRESS Serial No. Contract No. 19-144-11-54 07-202124 PROGRESS PAYMENT VOUCHER %complete: %time: 46% 20% Location: Federal Project: 07-LA-710-20.9/24.6 ACIM-710-1(839) Progress payment No. 013 Payment period ending: 05-20-19 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,768,313.60 1,863,126.35 2. a. Extra Work 901,336.73 108,287.07 b. Adustment Comp. 551,923.97 204,446.18 3. Materials on Hand 365,145.26 -23,117.78 4. Earned Subject to Retention 30,586,719.56 2,152,741.82 5. Mobilization 7,638,000.00 0.00 6. Total Work Completed 37,859,574.30 7. Deductions -67,781.70 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,156,937.86 2,102,741.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,102,741.82