Dept. of Trans. PROGRESS Serial No. Contract No. 20-023-09-29 07-202124 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 40% Location: Federal Project: 07-LA-710-20.9/24.6 ACIM-710-1(839) Progress payment No. 021 Payment period ending: 01-20-20 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 50,354,332.13 1,522,645.74 2. a. Extra Work 1,357,277.36 38,325.37 b. Adustment Comp. 1,277,676.15 22,874.82 3. Materials on Hand 250,737.59 -8,401.68 4. Earned Subject to Retention 53,240,023.23 1,575,444.25 5. Mobilization 8,040,000.00 0.00 6. Total Work Completed 61,029,285.64 7. Deductions -26,902.45 -14,687.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 61,253,120.78 1,560,756.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,560,756.75