Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-17-39 07-202124 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 80% Location: Federal Project: 07-LA-710-20.9/24.6 ACIM-710-1(839) Progress payment No. 040 Payment period ending: 08-20-21 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 74,480,026.24 10,696.95 2. a. Extra Work 2,701,188.50 14,526.00 b. Adustment Comp. 2,624,456.70 -5,787.28 3. Materials on Hand 4. Earned Subject to Retention 79,805,671.44 19,435.67 5. Mobilization 8,040,000.00 0.00 6. Total Work Completed 87,845,671.44 7. Deductions -83,943.07 -19,434.67 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 87,761,728.37 1.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1.00