Dept. of Trans. PROGRESS Serial No. Contract No. 01-115-10-21 07-202504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 16% 39% 07-LA-5-28.9/47.9 Federal Project: ACIM-005-3(995) Progress payment No. 04 Payment period ending: 04-20-01 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 01608 Total Estimate This Estimate 1. Contract Itms Without Mobil. 869,503.50 712,795.65 2.a. Extra Work 1,650.00 1,650.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 871,153.50 714,445.65 5. Mobilization 60,000.00 60,000.00 6. Total Work Completed 931,153.50 7. Deductions 8. a.Contract Retentions -87,115.35 -71,444.56 b. Unsatisfactory Prog. -0.01 -0.01 c. Reduction after 95% Comp. 9. Total pay to Contractor 844,038.14 703,001.08 10. Reduction Amt to Escrow 11. Payment to Escrow 87,110.00 12. Net Pymt. this Estimate 703,001.08