Dept. of Trans. PROGRESS Serial No. Contract No. 15-203-14-48 07-2055A4 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 18% Location: Federal Project: 07-LA-2-14.1/15.1 21L-6207(71) Progress payment No. 005 Payment period ending: 07-20-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,073,012.30 468,655.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,073,012.30 468,655.00 5. Mobilization 199,500.00 0.00 6. Total Work Completed 1,272,512.30 7. Deductions -117,163.75 -117,163.75 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,155,348.55 351,491.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 351,491.25