Dept. of Trans. PROGRESS Serial No. Contract No. 04-357-14-04 07-206044 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 33% 07-LA-5-0.0/13.5 Federal Project: ACST-X037(122) PHG-X037(122) Progress payment No. 03 Payment period ending: 12-20-04 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 86,663.51 86,663.51 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 447,012.31 -12,257.05 4. Earned Subject to Retention 533,675.82 74,406.46 5. Mobilization 58,520.00 0.00 6. Total Work Completed 145,183.51 7. Deductions -8,666.35 -8,666.35 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 583,529.47 65,740.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,740.11