Dept. of Trans. PROGRESS Serial No. Contract No. 05-298-10-00 07-206804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 20% 07-LA-60-R6.9/19.4 Federal Project: ACNH-P060(125) Progress payment No. 02 Payment period ending: 10-20-05 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 304,050.00 29,000.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 304,050.00 29,000.00 5. Mobilization 6. Total Work Completed 304,050.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 304,050.00 29,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 29,000.00