Dept. of Trans. PROGRESS Serial No. Contract No. 05-265-15-30 07-207104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 15% 41% 07-LA-164-5.6/8.7 Federal Project: ACST-S164(4) P-S164(4) Progress payment No. 01 Payment period ending: 09-20-05 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 165,730.87 165,730.87 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 165,730.87 165,730.87 5. Mobilization 7,500.00 7,500.00 6. Total Work Completed 173,230.87 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 173,230.87 173,230.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 173,230.87