Dept. of Trans. PROGRESS Serial No. Contract No. 16-173-11-50 07-207604 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 53% Location: Federal Project: 07-LA-101-S0.0/17.2 NHP-Q101(281) Progress payment No. 002 Payment period ending: 06-20-16 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614-5706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 621,004.43 534,255.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 621,004.43 534,255.90 5. Mobilization 161,500.00 161,500.00 6. Total Work Completed 782,504.43 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 782,504.43 695,755.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 695,755.90