Dept. of Trans. PROGRESS Serial No. Contract No. 06-116-07-57 07-214604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 61% 07-LA-5-2.0/ .0 Federal Project: ACIM-X037(130) ACNH-P060(128) Progress payment No. 04 Payment period ending: 04-20-06 TERNO INC 15701 HERON AVENUE LA MIRADA CA 90638 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,648.64 80,108.64 2.a. Extra Work 18,821.71 18,821.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 185,470.35 98,930.35 5. Mobilization 78,690.40 37,274.40 6. Total Work Completed 264,160.75 7. Deductions -3,900.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 260,260.75 136,204.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,204.75