Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 06-264-16-45 07-214604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5-2.0/ .0 Federal Project: ACIM-X037(130) ACNH-P060(128) Progress payment No. 09 Payment period ending: 08-29-06 TERNO INC 15701 HERON AVENUE LA MIRADA CA 90638 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 718,384.50 0.00 2.a. Extra Work 156,015.28 16,560.00 b. Adjustment Comp. -224,608.50 41,883.50 3. Materials on Hand 4. Earned Subject to Retention 649,791.28 58,443.50 5. Mobilization 82,832.00 0.00 6. Total Work Completed 732,623.28 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 722,623.28 58,443.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,443.50