Dept. of Trans. PROGRESS Serial No. Contract No. 14-083-14-00 07-215914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 57% 51% 07-LA-5-1.2/2.1 Federal Project: NONE Progress payment No. 26 Payment period ending: 03-20-14 C C MYERS INC P O BOX 2948 RANCHO CORDOVA CA 957412948 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,411,919.61 1,122,415.60 2.a. Extra Work 767,475.29 227,781.28 b. Adjustment Comp. 500,691.27 7,250.23 3. Materials on Hand 2,504,059.59 -110,897.30 4. Earned Subject to Retention 22,184,145.76 1,246,549.81 5. Mobilization 3,150,000.00 0.00 6. Total Work Completed 22,830,086.17 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,331,145.76 1,246,549.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,246,549.81