Dept. of Trans. PROGRESS Serial No. Contract No. 15-026-11-01 07-215944 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 35% 07-LA-5-4.0/5.8 Federal Project: NONE Progress payment No. 23 Payment period ending: 01-20-15 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 91353 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 51,328,112.65 1,315,529.36 2.a. Extra Work 1,762,919.08 154,299.14 b. Adjustment Comp. 2,351,295.53 182,006.16 3. Materials on Hand 2,247,534.09 0.00 4. Earned Subject to Retention 57,689,861.35 1,651,834.66 5. Mobilization 2,764,500.00 0.00 6. Total Work Completed 58,206,827.26 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 60,454,361.35 1,651,834.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,651,834.66