Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-14-20 07-215944 PROGRESS PAYMENT VOUCHER %complete: %time: 48% 37% Location: Federal Project: 07-LA-5-4.0/5.8 NONE Progress payment No. 024 Payment period ending: 02-20-15 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 91353 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,072,711.44 1,744,598.79 2. a. Extra Work 1,990,913.61 227,994.53 b. Adustment Comp. 2,466,926.29 115,630.76 3. Materials on Hand 2,247,534.09 0.00 4. Earned Subject to Retention 59,778,085.43 2,088,224.08 5. Mobilization 2,910,000.00 145,500.00 6. Total Work Completed 60,440,551.34 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 62,678,085.43 2,223,724.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,223,724.08