Dept. of Trans. PROGRESS Serial No. Contract No. 18-082-16-21 07-215944 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 82% Location: Federal Project: 07-LA-5-4.0/5.8 NONE Progress payment No. 061 Payment period ending: 03-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 91,070,482.19 2,192,715.53 2. a. Extra Work 4,650,934.23 53,419.82 b. Adustment Comp. 4,543,077.79 47,028.00 3. Materials on Hand 979,113.77 -148,523.27 4. Earned Subject to Retention 101,243,607.98 2,144,640.08 5. Mobilization 2,910,000.00 0.00 6. Total Work Completed 103,174,494.21 7. Deductions -29,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 104,124,607.98 2,141,640.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,141,640.08