Dept. of Trans. PROGRESS Serial No. Contract No. 18-113-21-47 07-215944 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 81% Location: Federal Project: 07-LA-5-4.0/5.8 NONE Progress payment No. 062 Payment period ending: 04-20-18 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 93,857,432.52 2,786,950.32 2. a. Extra Work 4,733,616.48 82,682.25 b. Adustment Comp. 4,543,077.79 0.00 3. Materials on Hand 387,640.82 -591,472.95 4. Earned Subject to Retention 103,521,767.61 2,278,159.62 5. Mobilization 2,910,000.00 0.00 6. Total Work Completed 106,044,126.79 7. Deductions -29,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 106,402,767.61 2,278,159.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,278,159.62