Dept. of Trans. PROGRESS Serial No. Contract No. 19-358-10-58 07-215954 PROGRESS PAYMENT VOUCHER %complete: %time: 85% 75% Location: Federal Project: 07-LA-5-5.8/6.8 CMLN-6207(68) Progress payment No. 071 Payment period ending: 12-20-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 62,074,992.66 380,747.23 2. a. Extra Work 6,791,245.85 52,673.49 b. Adustment Comp. 1,580,923.59 0.00 3. Materials on Hand 378,209.73 -67,018.00 4. Earned Subject to Retention 70,825,371.83 366,402.72 5. Mobilization 4,700,000.00 0.00 6. Total Work Completed 75,147,162.10 7. Deductions -34,843.54 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 75,490,528.29 366,402.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 366,402.72