Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-11-21 07-2159C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 55% 07-LA-5-1.8/3.0 Federal Project: IMOO-5294(9N) Progress payment No. 33 Payment period ending: 10-20-14 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MAROCS CA 90278 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,668,636.09 3,166,534.32 2.a. Extra Work 3,186,451.52 -3,875.18 b. Adjustment Comp. 183,498.40 0.00 3. Materials on Hand 4,146,946.82 -596,733.19 4. Earned Subject to Retention 48,185,532.83 2,565,925.95 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 50,038,586.01 7. Deductions 0.00 20,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 54,185,532.83 2,585,925.95 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,585,925.95