Dept. of Trans. PROGRESS Serial No. Contract No. 15-264-11-33 07-2159C4 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 65% Location: Federal Project: 07-LA-5-1.8/3.0 IMOO-5294(9N) Progress payment No. 044 Payment period ending: 09-20-15 FLATIRON WEST INC 1770 LA COSTA MEADOWS DRIVE SAN MAROCS CA 90278 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 56,217,999.04 2,950,285.97 2. a. Extra Work 4,246,731.72 751,758.59 b. Adustment Comp. 182,025.15 0.00 3. Materials on Hand 1,985,666.57 -1,305,403.49 4. Earned Subject to Retention 62,632,422.48 2,396,641.07 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 66,646,755.91 7. Deductions 0.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 68,632,422.48 2,397,641.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,397,641.07