Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 17-129-15-15 07-2159C4 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 83% Location: Federal Project: 07-LA-5-1.8/3.0 IMOO-5294(9N) Progress payment No. 065 Payment period ending: 04-20-17 FLATIRON WEST INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 78,133,101.15 290,500.00 2. a. Extra Work 5,953,701.63 15,712.40 b. Adustment Comp. 4,368,967.59 4,009,500.00 3. Materials on Hand 4. Earned Subject to Retention 88,455,770.37 4,315,712.40 5. Mobilization 6,000,000.00 0.00 6. Total Work Completed 94,455,770.37 7. Deductions -30,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 94,425,770.37 4,315,712.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,315,712.40