Dept. of Trans. PROGRESS Serial No. Contract No. 23-020-11-37 07-2159U4 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 83% Location: Federal Project: 07-LA-5-0.0/1.5 NHPI-052(981) DEMO-662(70) Progress payment No. 075 Payment period ending: 01-20-23 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 126,940,126.25 702,722.95 2. a. Extra Work 9,243,591.42 149,332.26 b. Adustment Comp. 1,868,220.48 0.00 3. Materials on Hand 54,080.51 -94,878.00 4. Earned Subject to Retention 138,106,018.66 757,177.21 5. Mobilization 8,900,000.00 0.00 6. Total Work Completed 146,951,938.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 147,006,018.66 757,177.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 757,177.21