Dept. of Trans. PROGRESS Serial No. Contract No. 04-146-12-58 07-2178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-134-6.1/6.8 Federal Project: ACNH-P134(29) Progress payment No. 20 Payment period ending: 05-20-04 J MC LOUGHLIN ENGINEERING CO INC 10722 ARROW RTE STE 716 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,421,344.49 -73,500.00 2.a. Extra Work 147,297.46 107,419.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,568,641.95 33,919.56 5. Mobilization 240,000.00 0.00 6. Total Work Completed 2,808,641.95 7. Deductions -550.00 0.00 8. a.Contract Retentions -128,432.10 -1,695.98 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,679,659.85 32,223.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 32,223.58