Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 04-363-09-29 07-2178U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-134-6.1/6.8 Federal Project: ACNH-P134(29) Progress payment No. 25 Payment period ending: 10-19-04 J MC LOUGHLIN ENGINEERING CO INC 10722 ARROW RTE STE 716 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,466,041.84 -23,487.50 2.a. Extra Work 248,955.64 1,385.00 b. Adjustment Comp. 21,583.57 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,736,581.05 -22,102.50 5. Mobilization 240,000.00 0.00 6. Total Work Completed 2,976,581.05 7. Deductions 0.00 550.00 8. a.Contract Retentions -137,934.18 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 137,934.18 137,934.18 9. Total pay to Contractor 2,976,581.05 116,381.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 116,381.68