Dept. of Trans. PROGRESS Serial No. Contract No. 06-025-07-48 07-222204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 54% 07-LA-10-14.5/15.3 Federal Project: ACIM-010-1(775) ACNH-P110(9) Progress payment No. 06 Payment period ending: 01-20-06 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,676,313.00 637,118.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 55,632.10 -2,497.95 4. Earned Subject to Retention 1,731,945.10 634,620.05 5. Mobilization 541,500.00 0.00 6. Total Work Completed 2,217,813.00 7. Deductions -19,924.92 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,253,520.18 634,620.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 634,620.05