Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-025-14-01 07-222204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-10-14.5/15.3 Federal Project: ACIM-010-1(775) ACNH-P110(9) Progress payment No. 16 Payment period ending: 09-18-06 BRUTOCO ENGINEERING AND CONSTRUCTION INC P O BOX 429 FONTANA CA 92334 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,015,277.51 3,024.00 2.a. Extra Work 126,013.35 20,980.09 b. Adjustment Comp. -27,934.73 -30,271.03 3. Materials on Hand 4. Earned Subject to Retention 5,113,356.13 -6,266.94 5. Mobilization 570,000.00 0.00 6. Total Work Completed 5,683,356.13 7. Deductions -37,000.00 12,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,646,356.13 5,733.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,733.06