Dept. of Trans. PROGRESS Serial No. Contract No. 08-143-09-31 07-222224 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 42% 07-LA-10-14.2/18.1 Federal Project: ACIM-X037(134) ACNH-P060(132) Progress payment No. 12 Payment period ending: 05-20-08 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE STE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,676,378.85 332,340.44 2.a. Extra Work 313,993.85 51,358.75 b. Adjustment Comp. 3. Materials on Hand 311,669.76 0.00 4. Earned Subject to Retention 5,302,042.46 383,699.19 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 6,510,372.70 7. Deductions -146,400.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,675,642.46 383,699.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,699.19