Dept. of Trans. PROGRESS Serial No. Contract No. 08-205-10-29 07-222224 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 42% 49% 07-LA-10-14.2/18.1 Federal Project: ACIM-X037(134) ACNH-P060(132) Progress payment No. 14 Payment period ending: 07-20-08 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE STE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,574,839.05 583,637.20 2.a. Extra Work 364,505.61 34,913.04 b. Adjustment Comp. 3. Materials on Hand 41,902.84 -269,766.92 4. Earned Subject to Retention 5,981,247.50 348,783.32 5. Mobilization 1,520,000.00 0.00 6. Total Work Completed 7,459,344.66 7. Deductions -196,400.00 -50,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,304,847.50 298,783.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,783.32