Dept. of Trans. PROGRESS Serial No. Contract No. 09-166-14-50 07-222224 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 90% 07-LA-10-14.2/18.1 Federal Project: ACIM-X037(134) ACNH-P060(132) Progress payment No. 26 Payment period ending: 06-20-09 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE STE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,495,612.88 128,910.00 2.a. Extra Work 578,757.09 29,055.48 b. Adjustment Comp. -15,573.47 0.00 3. Materials on Hand 4. Earned Subject to Retention 15,058,796.50 157,965.48 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 16,658,796.50 7. Deductions -309,300.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,349,496.50 157,965.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,965.48