Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-15-03 07-222224 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 99% 07-LA-10-14.2/18.1 Federal Project: ACIM-X037(134) ACNH-P060(132) Progress payment No. 28 Payment period ending: 08-20-09 BALFOUR BEATTY INFRASTRUCTURE INC 2333 COURAGE DRIVE STE C FAIRFIELD CA 94533 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,711,238.88 72,110.00 2.a. Extra Work 680,415.59 -7,083.76 b. Adjustment Comp. 93,769.82 109,343.29 3. Materials on Hand 4. Earned Subject to Retention 15,485,424.29 174,369.53 5. Mobilization 1,600,000.00 0.00 6. Total Work Completed 17,085,424.29 7. Deductions -309,300.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,776,124.29 174,369.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 174,369.53