Dept. of Trans. PROGRESS Serial No. Contract No. 06-144-10-24 07-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 10% 07-LA-170-18.8/19.8 Federal Project: NONE Progress payment No. 01 Payment period ending: 05-20-06 POWELL CONSTRUCTORS P O BOX 698 FONTANA CA 923341406 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 312,010.85 312,010.85 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 312,010.85 312,010.85 5. Mobilization 240,000.00 240,000.00 6. Total Work Completed 552,010.85 7. Deductions 8. a.Contract Retentions -31,201.09 -31,201.09 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 520,809.76 520,809.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 520,809.76