Dept. of Trans. PROGRESS Serial No. Contract No. 06-331-08-25 07-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 75% 07-LA-170-18.8/19.8 Federal Project: NONE Progress payment No. 07 Payment period ending: 11-20-06 POWELL CONSTRUCTORS P O BOX 698 FONTANA CA 923341406 Escrow No. 02244 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,638,839.30 555,737.00 2.a. Extra Work 8,300.73 8,300.73 b. Adjustment Comp. 3. Materials on Hand 16,424.58 16,424.58 4. Earned Subject to Retention 2,663,564.61 580,462.31 5. Mobilization 480,000.00 24,000.00 6. Total Work Completed 3,127,140.03 7. Deductions 8. a.Contract Retentions -133,178.23 -29,023.11 b. Unsatisfactory Prog. -29,023.12 -29,023.12 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,981,363.26 546,416.08 10. Reduction Amt to Escrow 11. Payment to Escrow 133,170.00 12. Net Pymt. this Estimate 546,416.08