Dept. of Trans. PROGRESS Serial No. Contract No. 07-054-13-21 07-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 100% 07-LA-170-18.8/19.8 Federal Project: NONE Progress payment No. 10 Payment period ending: 02-20-07 POWELL CONSTRUCTORS 8555 BANANA AVE FONTANA CA 92335-3019 Escrow No. 02244 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,531,257.30 276,543.40 2.a. Extra Work 27,655.36 11,508.67 b. Adjustment Comp. 125,315.06 125,315.06 3. Materials on Hand 0.00 -16,424.58 4. Earned Subject to Retention 4,684,227.72 396,942.55 5. Mobilization 480,000.00 0.00 6. Total Work Completed 5,164,227.72 7. Deductions 8. a.Contract Retentions -234,211.39 -19,847.13 b. Unsatisfactory Prog. -130,056.27 -19,847.13 c. Reduction after 95% Comp. 9. Total pay to Contractor 4,799,960.06 357,248.29 10. Reduction Amt to Escrow 11. Payment to Escrow 234,210.00 12. Net Pymt. this Estimate 357,248.29