Dept. of Trans. PROGRESS Serial No. Contract No. 07-082-13-03 07-224404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-170-18.8/19.8 Federal Project: NONE Progress payment No. 11 Payment period ending: 03-20-07 POWELL CONSTRUCTORS 8555 BANANA AVE FONTANA CA 92335-3019 Escrow No. 02244 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,631,596.00 100,338.70 2.a. Extra Work 32,004.05 4,348.69 b. Adjustment Comp. 125,315.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,788,915.11 104,687.39 5. Mobilization 480,000.00 0.00 6. Total Work Completed 5,268,915.11 7. Deductions 8. a.Contract Retentions -239,445.76 -5,234.37 b. Unsatisfactory Prog. 0.00 130,056.27 c. Reduction after 95% Comp. 9. Total pay to Contractor 5,029,469.35 229,509.29 10. Reduction Amt to Escrow 11. Payment to Escrow 239,440.00 12. Net Pymt. this Estimate 229,509.29