Dept. of Trans. PROGRESS Serial No. Contract No. 10-083-09-08 07-226514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 2% 07-VEN-1-11.6/28.5 Federal Project: SARR-X037(145) A-X037(145) Progress payment No. 01 Payment period ending: 03-20-10 TRAFFIC SOLUTIONS INC 8490 HARTMEYER LANE REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 199,825.00 199,825.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 199,825.00 199,825.00 5. Mobilization 24,225.00 24,225.00 6. Total Work Completed 224,050.00 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 224,050.00 224,050.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 224,050.00