Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-27 07-2266A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 36% 07-LA-5-27.2/28.7 Federal Project: NONE Progress payment No. 06 Payment period ending: 08-20-07 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335-3019 Escrow No. 02293 Total Estimate This Estimate 1. Contract Itms Without Mobil. 311,780.00 27,900.00 2.a. Extra Work 4,601.32 0.00 b. Adjustment Comp. 26,452.80 26,452.80 3. Materials on Hand 4. Earned Subject to Retention 342,834.12 54,352.80 5. Mobilization 235,000.00 0.00 6. Total Work Completed 577,834.12 7. Deductions 8. a.Contract Retentions -34,283.41 -5,435.28 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 543,550.71 48,917.52 10. Reduction Amt to Escrow 11. Payment to Escrow 34,280.00 12. Net Pymt. this Estimate 48,917.52