Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-12-21 07-2266A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 29% 07-LA-5-27.2/28.7 Federal Project: NONE Progress payment No. 15 Payment period ending: 06-20-08 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335-3019 Escrow No. 02293 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,018,004.20 267,795.20 2.a. Extra Work 27,585.46 1,262.50 b. Adjustment Comp. 48,673.15 0.00 3. Materials on Hand 0.00 -4,343.71 4. Earned Subject to Retention 1,094,262.81 264,713.99 5. Mobilization 446,500.00 94,000.00 6. Total Work Completed 1,540,762.81 7. Deductions 8. a.Contract Retentions -100,231.38 -17,276.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,440,531.43 341,437.49 10. Reduction Amt to Escrow 11. Payment to Escrow 100,230.00 12. Net Pymt. this Estimate 341,437.49