Dept. of Trans. PROGRESS Serial No. Contract No. 09-023-07-03 07-2266A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 49% 07-LA-5-27.2/28.7 Federal Project: NONE Progress payment No. 22 Payment period ending: 01-20-09 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335-3019 Escrow No. 02293 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,917,764.50 66,250.00 2.a. Extra Work 556,822.64 60,838.29 b. Adjustment Comp. 58,008.30 0.00 3. Materials on Hand 118,359.36 -43,743.42 4. Earned Subject to Retention 3,650,954.80 83,344.87 5. Mobilization 470,000.00 0.00 6. Total Work Completed 4,002,595.44 7. Deductions 8. a.Contract Retentions -182,547.74 -4,167.24 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,938,407.06 79,177.63 10. Reduction Amt to Escrow 11. Payment to Escrow 182,540.00 12. Net Pymt. this Estimate 79,177.63