Dept. of Trans. PROGRESS Serial No. Contract No. 09-056-11-12 07-2266A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 52% 07-LA-5-27.2/28.7 Federal Project: NONE Progress payment No. 23 Payment period ending: 02-20-09 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335-3019 Escrow No. 02293 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,242,034.50 324,270.00 2.a. Extra Work 672,510.56 115,687.92 b. Adjustment Comp. 58,008.30 0.00 3. Materials on Hand 78,111.71 -40,247.65 4. Earned Subject to Retention 4,050,665.07 399,710.27 5. Mobilization 470,000.00 0.00 6. Total Work Completed 4,442,553.36 7. Deductions 8. a.Contract Retentions -202,533.25 -19,985.51 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,318,131.82 379,724.76 10. Reduction Amt to Escrow 11. Payment to Escrow 202,530.00 12. Net Pymt. this Estimate 379,724.76