Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-13-02 07-2266A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 58% 07-LA-5-27.2/28.7 Federal Project: NONE Progress payment No. 25 Payment period ending: 04-20-09 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 92335-3019 Escrow No. 02293 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,701,909.60 223,825.10 2.a. Extra Work 769,904.45 90,801.57 b. Adjustment Comp. 58,008.30 0.00 3. Materials on Hand 0.00 -221,963.89 4. Earned Subject to Retention 4,529,822.35 92,662.78 5. Mobilization 470,000.00 0.00 6. Total Work Completed 4,999,822.35 7. Deductions 8. a.Contract Retentions -226,491.12 -4,633.14 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,773,331.23 88,029.64 10. Reduction Amt to Escrow 11. Payment to Escrow 226,490.00 12. Net Pymt. this Estimate 88,029.64