Dept. of Trans. PROGRESS Serial No. Contract No. 08-053-11-29 07-228004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 32% 07-LA-110 Federal Project: ACST-X035(135) PH-X035(135) Progress payment No. 04 Payment period ending: 02-20-08 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 173,277.80 78,934.30 2.a. Extra Work 184.67 184.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 173,462.47 79,118.97 5. Mobilization 82,500.00 27,500.00 6. Total Work Completed 255,962.47 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 255,962.47 106,618.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,618.97