Dept. of Trans. PROGRESS Serial No. Contract No. 08-113-12-18 07-228004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 50% 07-LA-110 Federal Project: ACST-X035(135) PH-X035(135) Progress payment No. 06 Payment period ending: 04-20-08 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 398,422.10 97,240.50 2.a. Extra Work 6,089.28 1,573.17 b. Adjustment Comp. 3. Materials on Hand 55,838.49 55,838.49 4. Earned Subject to Retention 460,349.87 154,652.16 5. Mobilization 104,500.00 0.00 6. Total Work Completed 509,011.38 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 564,849.87 154,652.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,652.16