Dept. of Trans. PROGRESS Serial No. Contract No. 08-086-11-23 07-231314 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 79% 07-LA-2 Federal Project: ACIM-X037(132) ACNH-X037(133) Progress payment No. 12 Payment period ending: 03-20-08 POWELL CONSTRUCTORS 8555 BANANA AVENUE FONTANA CA 923353019 Escrow No. 02325 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,929,507.00 117,820.00 2.a. Extra Work 183,978.16 38,537.05 b. Adjustment Comp. 8,230.40 1,474.80 3. Materials on Hand 4. Earned Subject to Retention 7,121,715.56 157,831.85 5. Mobilization 800,000.00 0.00 6. Total Work Completed 7,921,715.56 7. Deductions 8. a.Contract Retentions -356,085.78 -7,891.59 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,565,629.78 149,940.26 10. Reduction Amt to Escrow 11. Payment to Escrow 356,080.00 12. Net Pymt. this Estimate 149,940.26