Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-13-43 07-231404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 79% 07-LA-210-40.6/42.1 Federal Project: NONE Progress payment No. 16 Payment period ending: 04-20-09 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02346 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,053,387.84 248,564.90 2.a. Extra Work 53,984.70 2,909.74 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 6,107,372.54 251,474.64 5. Mobilization 750,000.00 0.00 6. Total Work Completed 6,857,372.54 7. Deductions 8. a.Contract Retentions -305,368.63 -12,573.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,552,003.91 238,900.91 10. Reduction Amt to Escrow 11. Payment to Escrow 305,360.00 12. Net Pymt. this Estimate 238,900.91