Dept. of Trans. PROGRESS Serial No. Contract No. 09-329-13-33 07-231404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-210-40.6/42.1 Federal Project: NONE Progress payment No. 20 Payment period ending: 11-20-09 O DONNELL CONSTRUCTION INC 559 W COVINA BLVD SAN DIMAS CA 917732911 Escrow No. 02346 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,525,930.12 80,191.01 2.a. Extra Work 105,177.84 -11,192.95 b. Adjustment Comp. 10,120.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,641,227.96 68,998.06 5. Mobilization 750,000.00 0.00 6. Total Work Completed 8,391,227.96 7. Deductions 8. a.Contract Retentions -382,061.40 -3,449.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,009,166.56 65,548.16 10. Reduction Amt to Escrow 11. Payment to Escrow 382,060.00 12. Net Pymt. this Estimate 65,548.16