Dept. of Trans. PROGRESS Serial No. Contract No. 07-053-15-23 07-232304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 19% 38% 07-LA-101-0.6/10.4 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-07 PETERSON CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 926145706 Escrow No. 02259 Total Estimate This Estimate 1. Contract Itms Without Mobil. 358,645.64 110,612.45 2.a. Extra Work 22,219.81 7,650.11 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 380,865.45 118,262.56 5. Mobilization 198,750.00 66,250.00 6. Total Work Completed 579,615.45 7. Deductions 8. a.Contract Retentions -38,086.55 -11,826.26 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 541,528.90 172,686.30 10. Reduction Amt to Escrow 11. Payment to Escrow 38,080.00 12. Net Pymt. this Estimate 172,686.30