Dept. of Trans. PROGRESS Serial No. Contract No. 07-264-15-57 07-2324A4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-LA-5-13.9/41.0 Federal Project: NONE Progress payment No. 11 Payment period ending: 09-20-07 A C C U CONSTRUCTION INC 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 393,778.00 3,500.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 393,778.00 3,500.00 5. Mobilization 60,000.00 0.00 6. Total Work Completed 453,778.00 7. Deductions -8,222.00 0.00 8. a.Contract Retentions -19,688.90 -175.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 425,867.10 3,325.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,325.00