Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-15-10 07-2324F4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 07-VEN-33-0.0/7.0 Federal Project: NONE Progress payment No. 14 Payment period ending: 11-20-07 AMERICA WEST LANDSCAPE INC P O BOX 1698 BELLFLOWER CA 90707 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 617,101.07 2,751.20 2.a. Extra Work 10,865.58 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 627,966.65 2,751.20 5. Mobilization 43,448.42 0.00 6. Total Work Completed 671,415.07 7. Deductions -2,042.70 0.00 8. a.Contract Retentions -31,398.33 -137.56 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 637,974.04 2,613.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,613.64