Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-123-08-51 07-232604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 07-LA-5-15.9/17.1 Federal Project: ACIM-X037(131) ACNH-P060(129) Progress payment No. 07 Payment period ending: 04-02-07 ALL AMERICAN ASPHALT P O BOX 2229 CORONA CA 92878 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 752,804.20 39,366.00 2.a. Extra Work 6,115.74 6,115.74 b. Adjustment Comp. -13,060.50 -13,060.50 3. Materials on Hand 4. Earned Subject to Retention 745,859.44 32,421.24 5. Mobilization 18,000.00 0.00 6. Total Work Completed 763,859.44 7. Deductions -28,600.00 -5,962.50 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 735,259.44 26,458.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,458.74